Alabama gives suppliers four months to file, and the notice has to come before that
If you sell materials into Alabama jobs and you don't have a contract with the owner, there's an order of operations you can't skip. You send the owner a Notice of Unpaid Lien first. The lien itself comes after that, and it has to be filed within four months of your last delivery.
That sounds simple. Where it goes wrong is that people treat the notice as paperwork they can catch up on later. It isn't. Skipping it is the most common reason suppliers lose a lien claim in Alabama, and a lien filed without it can be thrown out even if the filing date was fine.
The three dates to keep on the job file
- Your last delivery date. The four-month filing window counts from here.
- The date you sent the Notice of Unpaid Lien. Keep proof, and send it early enough that it clearly comes before the filing.
- The date the debt became due. The suit to enforce has to be filed within six months of that.
Notice that last one doesn't count from the filing. If the invoice went past due well before you filed, you may have less time to sue than you'd guess.
A habit that helps
When a pay app on an Alabama job slips past 30 days, pull the delivery tickets that day and work out the four-month date. If the notice hasn't gone out yet, that's the moment to send it, not the week before the filing deadline.
The statutes are Ala. Code ยง 35-11-210 and the sections that follow it. We keep a short summary in our Alabama lien deadlines for material suppliers page, with the common mistakes listed out.
From the LienDeadline team. General information, not legal advice; have a qualified reviewer check the facts on any live job.