Maryland lien claims start in circuit court, not at the recorder

Suppliers used to recording a lien form at the county are often caught off guard in Maryland. There, you establish a mechanics lien by filing a petition in circuit court in the county where the land sits, within 180 days after the work is finished or the materials are furnished.

Subcontractors and suppliers also owe the owner written notice within 120 days after their work or furnishing, sent by registered or certified mail with return receipt, or delivered personally. Once the first petition is filed, the enforcement petition is due within one year. Owner-residence dwellings come with their own payment limits, so check the project type before you rely on the dates.

The notice, petition and enforcement dates are on LienDeadline's page on Maryland mechanics lien deadlines.

From the LienDeadline team. General information, not legal advice. Have a qualified reviewer check the facts on any live job.