Ohio lien filing: 60 days or 75 days, and why the property type decides it

Ohio gives material suppliers two ordinary filing windows, and which one applies depends on what was built.

A qualifying oil or gas claim has its own 120-day period, with separate conditions.

The notice of furnishing depends on the commencement notice

If you're an indirect supplier and a notice of commencement has been recorded, the notice of furnishing is generally due 21 days after your first furnishing. Suppliers hired directly by the owner, and some home-construction contracts, are exceptions. If the commencement notice was recorded late, or a requested copy was never served, your notice deadline can be extended under §1311.04(I)–(J).

Don't stop at recording

You also have to serve a copy of the recorded affidavit on the owner, part owner or lessee within 30 days after filing (§1311.07).

We keep the full breakdown in our Ohio mechanics lien deadlines for suppliers page.

From the LienDeadline team. General information, not legal advice; have a qualified reviewer check the facts on any live job.