Tennessee's first 90 days is a monthly notice, not the lien itself

Tennessee suppliers usually run into three separate 90-day clocks, and the first one starts while the job still feels routine.

When a month's materials go unpaid, a Notice of Non-Payment for that month is due within 90 days of the supply month. Deliver in April, May and June with nothing collected and you are looking at three notice windows, not one shared deadline. The month people skip is almost always the earliest one, because nobody wants to "make it formal" while they still expect the check.

The lien filing itself is due within 90 days after the project is completed or abandoned. Treat that date as fixed — don't count on a weekend or holiday for extra time. Then a foreclosure suit has to be filed within 90 days after the lien is filed. Put that date on the calendar the same day you record.

The statutes are Tenn. Code Ann. § 66-11-101 and following (including §§ 66-11-112, 66-11-145 and 66-11-146). LienDeadline's short page on Tennessee's three 90-day lien deadlines lists the common supplier mistakes. Its public calculator does not compute Tennessee dates, so project facts there go to qualified review.

From the LienDeadline team. General information, not legal advice; have a qualified reviewer check the facts on any live job.