Wisconsin's six-month lien window is really about five
Wisconsin gives a supplier six months from last furnishing to file a lien claim. It's easy to read that as six months of slack, and that's the mistake.
Before you can file, the owner has to get a notice of intent to file at least 30 days ahead, and that applies even on jobs where no preliminary notice was required. So the real last day to act is about five months out, not six. If you send the notice of intent late, a timely filing can't happen.
The filing itself goes to the clerk of circuit court in the county where the land is, not the county recorder, and the owner gets a copy within 30 days after filing. After that the claim has to be enforced by a lawsuit within two years of filing.
Many projects also need a written notice within 60 days of first furnishing, with exemptions for some direct-owner, nonresidential and larger residential work. A late one only covers material delivered after the owner actually gets it.
LienDeadline's Wisconsin lien notice and filing guide lists each step with its statute section.
From the LienDeadline team. General information, not legal advice. Check the facts of a live job with qualified Wisconsin counsel.