The zero-dollar ticket problem: when the newest date isn't your last furnishing date
Here's a pattern that shows up in supplier files all the time. Main order delivered. A couple of backordered pieces go out a week later. Then, two weeks after that, a single replacement part ships on a zero-dollar ticket marked "replace damaged item." A credit memo follows.
Someone pulls the latest date in the account and counts the lien deadline from it. That's the mistake.
Price doesn't decide it, purpose does
A zero-dollar ticket can be real furnishing or it can be a fix. The question is whether it supplied scope that was still outstanding, or corrected a problem with material already delivered. Florida makes this concrete: its definition of final furnishing in ยง 713.01(12) excludes correcting deficiencies in work or materials already supplied. Other states use different triggers, so don't carry Florida's rule everywhere.
What to sort before you pick a date
- Backorder shipment: did it supply outstanding project scope?
- Replacement ticket: did it complete scope, or correct a deficiency?
- Return or credit: a credit memo isn't a delivery.
- Late invoice: which actual deliveries does it bill?
Write the reasoning down
If the reviewer decides the backorder finished the scope and the replacement was a fix, put that in the job file with the records behind it. If the replacement's purpose is still disputed, leave the date under review. Don't quietly pick the later date because it buys time, or the earlier one because it feels safer. And if you correct a date in your records, that changes your record, not the law's clock.
We wrote up a longer version with a worked example, covering how to check a final-furnishing date before you count from it.
From the LienDeadline team. General information, not legal advice; have a qualified reviewer check the facts on any live job.